ZeroTrust Atlas Spatial Operating Environment

Kogi Limestone Exploration Survey

SUR-KOG-MINE-011 · Topographic

Authoritative survey project

Kogi Limestone Exploration Survey

Mining survey programme demonstrating the multi-discipline Atlas platform.

Active Mining & Natural Resources EPSG:4326
Exploration blocks 36 active
Boreholes 128 located
Region Kogi
Sector Mining

Teams

1

Assigned field authorities

Control points

11

Registered monuments

Verified

9

Accepted through QA

Progress

In field

Current delivery state

Project authority

Professional identity and governance

Reference
SUR-KOG-MINE-011
Client
Mining Programme Authority
Principal surveyor
Mining Survey Lead
Measurement system
Metric
Horizontal CRS
EPSG:4326
Vertical datum
EGM2008

Programme schedule

Operational delivery window

Start date
15 Jul 2026
Target completion
08 Oct 2026
Completed
Open programme
Last activity
2 hours ago

Assigned survey teams

Crews authorized to operate this project

ATLAS-FAABCF8B

Atlas Mining Division

Mining Survey Lead

Operational

Quality posture

Current control-network assurance

82% control points verified

Mission operations

Live field execution attached to this Survey project

MSN-SUR-KOG-MINE-011

Kogi Limestone Exploration Survey Mission

Completed
Project
Kogi Limestone Exploration Survey
Phase
Completed
Priority
Normal
Risk
Low
Mission progress 100%
100%

Control-point register

Authoritative geodetic and project control

MIN-001

SUR-KOG-MINE-011 Control 001

Type
Control
Condition
Verified
Coordinates
7.73425, 6.690875
Grid
E 500125.25 · N 700141.75
Horizontal accuracy
0.0101 m
Vertical accuracy
0.0201 m

MIN-002

SUR-KOG-MINE-011 Control 002

Type
Control
Condition
Verified
Coordinates
7.7348, 6.69115
Grid
E 500250.5 · N 700283.5
Horizontal accuracy
0.0102 m
Vertical accuracy
0.0202 m

MIN-003

SUR-KOG-MINE-011 Control 003

Type
Control
Condition
Verified
Coordinates
7.73535, 6.691425
Grid
E 500375.75 · N 700425.25
Horizontal accuracy
0.0103 m
Vertical accuracy
0.0203 m

MIN-004

SUR-KOG-MINE-011 Control 004

Type
Control
Condition
Verified
Coordinates
7.7359, 6.6917
Grid
E 500501 · N 700567
Horizontal accuracy
0.0104 m
Vertical accuracy
0.0204 m

MIN-005

SUR-KOG-MINE-011 Control 005

Type
Control
Condition
Established
Coordinates
7.73645, 6.691975
Grid
E 500626.25 · N 700708.75
Horizontal accuracy
0.0105 m
Vertical accuracy
0.0205 m

MIN-006

SUR-KOG-MINE-011 Control 006

Type
Control
Condition
Verified
Coordinates
7.737, 6.69225
Grid
E 500751.5 · N 700850.5
Horizontal accuracy
0.0106 m
Vertical accuracy
0.0206 m

MIN-007

SUR-KOG-MINE-011 Control 007

Type
Control
Condition
Verified
Coordinates
7.73755, 6.692525
Grid
E 500876.75 · N 700992.25
Horizontal accuracy
0.0107 m
Vertical accuracy
0.0207 m

MIN-008

SUR-KOG-MINE-011 Control 008

Type
Control
Condition
Verified
Coordinates
7.7381, 6.6928
Grid
E 501002 · N 701134
Horizontal accuracy
0.0108 m
Vertical accuracy
0.0208 m

MIN-009

SUR-KOG-MINE-011 Control 009

Type
Control
Condition
Verified
Coordinates
7.73865, 6.693075
Grid
E 501127.25 · N 701275.75
Horizontal accuracy
0.0109 m
Vertical accuracy
0.0209 m

MIN-010

SUR-KOG-MINE-011 Control 010

Type
Control
Condition
Established
Coordinates
7.7392, 6.69335
Grid
E 501252.5 · N 701417.5
Horizontal accuracy
0.011 m
Vertical accuracy
0.021 m

MIN-011

SUR-KOG-MINE-011 Control 011

Type
Control
Condition
Verified
Coordinates
7.73975, 6.693625
Grid
E 501377.75 · N 701559.25
Horizontal accuracy
0.0111 m
Vertical accuracy
0.0211 m

Operational deliverables

Survey outputs prepared for Atlas

Terrain model
Sample register
Resource map

Project actions

Continue the operational workflow